The MICIC Nominees Trust t/a Capital Projects & Developments & Red Ink Homes Pty Ltd [2013] WASAT 117

Construction Contracts Act 2004 (WA) - From when time runs, pursuant to implied term cl 7(3) Sch 1 Div 5 of Construction Contracts Act 2004 (WA) - Section 61(1)(b), (e) and (h) of the Interpretation Act 1984 (WA) – Specified day - Specified event - Common law rules on computation of time - Is the time for an event the whole day? - When does a payment dispute arise? - Is the day on which the payment dispute arises to be included or excluded when calculating 'within 28 days after the dispute arises' for s 26 of Construction Contracts Act 2004 (WA)? - Relevance of privity of contract as to whether application was prepared and served in accordance with s 26 of Construction Contracts Act 2004 (WA)